V&V Manager Skill (Verification & Validation)
Read
CONVENTIONS.mdat the repo root before proceeding.
This skill closes the engineering loop. It compares "As-Required" (from requirements-manager) against "As-Analyzed" or "As-Tested" (from domain skills and ait-manager).
Before You Begin
Ask the user (if not already known):
- What V&V standard applies?
- NASA: NPR 7123.1 (SE Processes), NASA-STD-8739 series
- ESA: ECSS-E-ST-10-02 (Verification)
- INCOSE: Systems Engineering Handbook Ch. 12
- What design phase? (Determines which verification methods are expected to have evidence)
- Phase A/B: Analysis only — most items will be OPEN
- Phase C: Analysis and some inspection
- Phase D: Test evidence becomes available
- Where are the analysis outputs stored? Default:
/analysis/[skill-name]/
Applicable Phases
- Primary: Phase B (verification planning), Phase C/D (verification execution and closure)
- Supporting: Phase A (define verification approach per requirement)
Core Workflow
1. Requirement Lookup
- Scan
/requirements/for### [REQ-ID]headers. - For each requirement, identify the specified Verification Method: Test, Analysis, Inspection, or Demonstration (TAID).
2. Evidence Retrieval
- Search
/analysis/for corresponding output files. - Match logic:
- REQ-PWR-* → look in
/analysis/power-assessment/ - REQ-THR-* → look in
/analysis/thermal-assessment/ - REQ-STR-* → look in
/analysis/structural-assessment/ - etc.
- REQ-PWR-* → look in
- If evidence exists: compare the result against the requirement threshold.
- If evidence is missing: flag as OPEN and recommend which skill to run.
3. Phase-Appropriate Expectations
| Verification Method | Phase A | Phase B | Phase C | Phase D | |:---|:---|:---|:---|:---| | Analysis | OPEN (expected) | Should have evidence | Must have evidence | Must have evidence | | Test | OPEN | OPEN | OPEN (test planned) | Must have evidence | | Inspection | OPEN | OPEN | May have evidence | Must have evidence | | Demonstration | OPEN | OPEN | OPEN | Should have evidence |
4. VCM Generation
Create a master table:
| ID | Requirement | Method | Evidence File | Status | Notes |
|:---|:---|:---|:---|:---|:---|
| REQ-PWR-001 | Battery ≥ 1500 Wh EOL | Analysis | power_analysis.md | 🟢 PASS | 1620 Wh predicted |
| REQ-THR-003 | Battery 0-30°C operating | Analysis | thermal_model.md | 🟡 OPEN | Pending thermal run |
| REQ-STR-010 | First freq > 25 Hz | Test | — | 🔴 OPEN | No test yet |
Compliance Rules
- PASS 🟢: Evidence exists and values meet requirement (including margins).
- FAIL 🔴: Evidence exists but values exceed limits.
- OPEN 🟡: No evidence yet or evidence is from a previous design iteration.
- WAIVER: Requirement formally relaxed with documented justification.
Output Format
- Verification Control Matrix (
vcm.md): Master tracking table. - Analysis Requests: List of "To-Do" assessments to close OPEN requirements.
- Compliance Summary: Overall percentage of PASS/FAIL/OPEN, with traffic light status.
Interface
- Reads from:
/requirements/,/analysis/*/(all domain skill outputs),/analysis/ait-manager/(test evidence) - Writes to:
/analysis/v-and-v-manager/ - Consumed by: Review boards (SRR, PDR, CDR), project management