agile-planning

使用独特的冲刺代码生成包含冲刺和路线图的敏捷发布计划。在创建冲刺时间表、产品路线图、发布计划,或当用户提到敏捷计划、冲刺、路线图或发布计划时使用。

person作者: jakexiaohubgithub

Agile Planning

Generate lean agile release plans with sprint schedules and roadmaps.

Overview

This skill creates structured release plans for agile projects. It generates:

  • Sprint schedules with unique codes (SPRINT-001, SPRINT-002, etc.)
  • Tasks with ticket codes (T-001, T-002, etc.) for granular tracking
  • Roadmaps showing timeline and milestones
  • Dependencies and release checkpoints

Use this when planning product releases, organizing work into sprints, or communicating timelines to stakeholders.

Instructions

Step 1: Gather Context

Before generating a plan, collect:

  • Project scope: What are we building?
  • Timeline: How many weeks/months?
  • Team size: Number of developers
  • Sprint duration: Typically 2 weeks
  • Key milestones: Alpha, beta, production dates
  • Priorities: Must-have vs nice-to-have features

Step 2: Structure Sprints

Create sprints with:

  • Unique codes: SPRINT-001, SPRINT-002, SPRINT-003 (sequential, zero-padded)
  • Sprint theme: Descriptive name (e.g., "Payment Integration", "UI Polish")
  • Duration: Start and end dates
  • Goal: One-sentence sprint objective
  • Tasks: 3-5 concrete tasks per sprint, each with unique ticket code (T-001, T-002, etc.)
  • Dependencies: What blocks this sprint or depends on it

Task Numbering:

  • Use format: T-001, T-002, T-003 (zero-padded, sequential across entire release)
  • Each task gets a unique code that persists throughout the project
  • Never reuse task codes

Sprint Duration Guidelines:

  • 2 weeks (most common) = 10 working days
  • Plan for 80% capacity (reserve 20% for meetings, bugs, unexpected)
  • Balance workload across sprints

Sprint Themes: Use clear, goal-oriented themes:

  • Foundation, Setup, Infrastructure
  • Core Features, MVP Development
  • Integration, API Development
  • Testing, Bug Fixes, Optimization
  • Beta Launch, Production Release

Step 3: Build Roadmap

Group sprints into timeline view:

  • By Quarter: Q1 2025, Q2 2025, etc.
  • By Month: January, February, March
  • By Phase: Foundation → Features → Launch

Include major milestones:

  • Alpha release dates
  • Beta release dates
  • Production launch
  • Key feature completions

Step 4: Format Output

Use this structure:

# Release Plan: [Project Name] v[Version]

**Release Goal**: [One sentence]
**Timeline**: [Start] - [End] ([X] sprints)
**Team**: [Number] developers

## Sprints

### SPRINT-001: [Theme]
**Duration**: [Start Date] - [End Date]
**Goal**: [What this sprint achieves]

**Tasks**:
- T-001: [Task description] [ ]
- T-002: [Task description] [ ]
- T-003: [Task description] [ ]

**Dependencies**: [If any]

### SPRINT-002: [Theme]
**Duration**: [Start Date] - [End Date]
**Goal**: [What this sprint achieves]

**Tasks**:
- T-004: [Task description] [ ]
- T-005: [Task description] [ ]

## Roadmap

### Q1 2025
- **SPRINT-001**: [Key achievement]
- **SPRINT-002**: [Key achievement]

### Q2 2025
- **SPRINT-003**: [Key achievement]

## Milestones
- **[Date]**: Alpha release (SPRINT-00X)
- **[Date]**: Beta release (SPRINT-00X)
- **[Date]**: Production launch (SPRINT-00X)

Step 5: Validate Plan

Check:

  • ✓ Sprint codes are sequential and unique (SPRINT-001, SPRINT-002, etc.)
  • ✓ Task codes are sequential and unique (T-001, T-002, etc.)
  • ✓ Tasks are specific and measurable
  • ✓ Dependencies are identified
  • ✓ Timeline is realistic
  • ✓ Milestones align with sprint schedule

Best Practices

Sprint Planning:

  • Keep tasks specific: "T-001: Stripe SDK integration" not "T-001: work on payments"
  • Limit to 3-5 tasks per sprint
  • Front-load risky/complex work
  • Include buffer sprint for testing

Task Numbering:

  • Always use 3 digits: T-001, not T-1
  • Sequential across entire release (T-001, T-002... T-050)
  • Never reuse codes, even if task is cancelled

Dependencies:

  • Identify early: "Requires SPRINT-001 API endpoints"
  • Schedule dependent sprints sequentially
  • Document external dependencies (APIs, design assets)

Roadmap:

  • Focus on outcomes, not tasks
  • Highlight major milestones
  • Keep it stakeholder-friendly
  • Update after each sprint

Code Conventions:

  • Sprints: Always use 3 digits (SPRINT-001, not SPRINT-1)
  • Tasks: Always use 3 digits (T-001, not T-1)
  • Sequential numbering: Task codes continue across all sprints
  • Never reuse codes (sprints or tasks)

Examples

Example 1: E-commerce Platform (6 sprints)

# Release Plan: E-commerce Platform v2.0

**Release Goal**: Launch new checkout system with multiple payment options
**Timeline**: Jan 1 - Mar 15, 2025 (6 sprints)
**Team**: 3 developers

## Sprints

### SPRINT-001: Payment Foundation
**Duration**: Jan 1 - Jan 14
**Goal**: Setup payment infrastructure and API integrations

**Tasks**:
- T-001: Stripe SDK integration [ ]
- T-002: Payment database schema design [ ]
- T-003: Payment API endpoints [ ]
- T-004: Shipping cost calculator [ ]

**Dependencies**: None

---

### SPRINT-002: Checkout UI
**Duration**: Jan 15 - Jan 28
**Goal**: Build responsive checkout flow

**Tasks**:
- T-005: Guest checkout form [ ]
- T-006: Address autosave feature [ ]
- T-007: Mobile responsive layout [ ]
- T-008: Form validation logic [ ]

**Dependencies**: Requires SPRINT-001 payment API (T-003)

---

### SPRINT-003: PayPal Integration
**Duration**: Jan 29 - Feb 11
**Goal**: Add PayPal as payment option

**Tasks**:
- T-009: PayPal SDK setup [ ]
- T-010: Payment method selector UI [ ]
- T-011: Order confirmation emails [ ]
- T-012: Transaction logging system [ ]

**Dependencies**: Requires SPRINT-001 infrastructure (T-002, T-003)

---

### SPRINT-004: Testing & Polish
**Duration**: Feb 12 - Feb 25
**Goal**: Ensure production readiness

**Tasks**:
- T-013: End-to-end testing suite [ ]
- T-014: Bug fixes from QA [ ]
- T-015: Performance optimization [ ]
- T-016: Security review and fixes [ ]

**Dependencies**: All features complete (T-001 through T-012)

---

### SPRINT-005: Beta Launch
**Duration**: Feb 26 - Mar 11
**Goal**: Soft launch to beta users

**Tasks**:
- T-017: Beta deployment to staging [ ]
- T-018: User feedback collection system [ ]
- T-019: Analytics and tracking setup [ ]
- T-020: Critical bug fixes [ ]

**Dependencies**: SPRINT-004 testing complete (T-013)

---

### SPRINT-006: Production Release
**Duration**: Mar 12 - Mar 15
**Goal**: Full production rollout

**Tasks**:
- T-021: Production deployment [ ]
- T-022: Monitoring and alerting setup [ ]
- T-023: User documentation [ ]
- T-024: Team handoff and training [ ]

**Dependencies**: Beta success metrics met (T-017, T-018)

## Roadmap

### Q1 2025
- **SPRINT-001**: Payment infrastructure complete
- **SPRINT-002**: Checkout UI launched
- **SPRINT-003**: PayPal support added
- **SPRINT-004**: Testing complete, production-ready
- **SPRINT-005**: Beta launch successful
- **SPRINT-006**: Full production release

## Milestones
- **Feb 25**: Alpha release (internal testing)
- **Feb 26**: Beta release (limited users)
- **Mar 12**: Production launch (all users)

Example 2: Mobile App MVP (4 sprints)

# Release Plan: Fitness Tracker App v1.0

**Release Goal**: Launch MVP with core tracking features
**Timeline**: 8 weeks (4 sprints)
**Team**: 2 developers

## Sprints

### SPRINT-001: User Foundation
**Duration**: Week 1-2
**Goal**: User accounts and authentication

**Tasks**:
- T-001: Firebase authentication setup [ ]
- T-002: User profile creation flow [ ]
- T-003: Profile editing functionality [ ]
- T-004: Avatar upload feature [ ]

### SPRINT-002: Activity Tracking
**Duration**: Week 3-4
**Goal**: Core fitness tracking features

**Tasks**:
- T-005: Step counter integration [ ]
- T-006: Manual activity logging interface [ ]
- T-007: Activity history view [ ]
- T-008: Basic statistics dashboard [ ]

### SPRINT-003: Data Visualization
**Duration**: Week 5-6
**Goal**: Charts and progress tracking

**Tasks**:
- T-009: Daily activity charts [ ]
- T-010: Weekly summary view [ ]
- T-011: Goal progress indicators [ ]
- T-012: Achievement badges system [ ]

### SPRINT-004: Launch Prep
**Duration**: Week 7-8
**Goal**: Polish and release

**Tasks**:
- T-013: App store assets creation [ ]
- T-014: Beta testing coordination [ ]
- T-015: Critical bug fixes [ ]
- T-016: Production deployment [ ]

## Roadmap

### Month 1
- SPRINT-001: User system live
- SPRINT-002: Activity tracking functional

### Month 2
- SPRINT-003: Data visualization complete
- SPRINT-004: MVP launched to app stores

## Milestones
- **Week 6**: Beta testing begins
- **Week 8**: App store submission
- **Week 9**: Public launch

Reference Files

For more detailed guidance:

When to Use

Use this skill when:

  • Starting a new product release
  • Planning quarterly roadmaps
  • Breaking down large projects into sprints
  • Communicating timelines to stakeholders
  • Organizing backlog into time-boxed iterations
  • Creating sprint schedules for agile teams