execution-plan-generator

覆盖WIP限制(如果省略则自动计算)

person作者: jakexiaohubgithub

Execution Plan Generator

Generates a structured sprint execution plan from a GitHub epic. Analyzes issues, infers dependencies, assigns parallel lanes, and outputs a sprint-runner-compatible markdown plan.

Quick Start

Given repo owner/repo and epic #42, generate an execution plan.

How It Works

Phase 1: Issue Collection

Detect the tracker type first. The plan's tracker config field determines how to fetch issues:

GitHub Issues (default)

# Get the epic issue body (contains task list with issue references)
gh issue view {epic} --repo {repo} --json title,body,labels

# Extract referenced issue numbers from the epic body
# Patterns: - [ ] #N, - [x] #N, #N, {repo}#N

# Fetch each referenced issue
gh issue view {N} --repo {repo} --json number,title,body,labels,state,assignees

If the epic uses a milestone instead:

gh issue list --repo {repo} --milestone "{milestone}" --state all --json number,title,body,labels,assignees --limit 100

Linear

# Use linear CLI or GraphQL API
linear issue list --project "{project_name}" --state "Backlog,Todo,In Progress"
# Or fetch by parent issue identifier

Important: Don’t assume tracker type from the repo. Check the plan config or ask.

Phase 2: Issue Analysis

For each issue, extract structured data from the body:

  1. Title keywords — classify by type (contract, schema, security, adapter, test, docs, config)
  2. Acceptance criteria — look for ## Acceptance Criteria, ## AC, - [ ] checklists
  3. File hints — paths mentioned in body (src/, pkg/, *.go, *.ts, etc.)
  4. Explicit dependencies — phrases like "depends on #N", "after #N", "requires #N", "blocked by #N"
  5. Labels — priority labels (P0, P1, P2), type labels (bug, feature, security)

Phase 3: Codebase Analysis (Optional)

If clone: true or a local clone exists:

# Clone to temp directory
git clone --depth 1 https://github.com/{repo}.git /tmp/plan-{repo_name}

# Analyze structure
find . -name '*.go' -o -name '*.ts' -o -name '*.py' -o -name '*.rs' | head -200
cat go.mod 2>/dev/null || cat package.json 2>/dev/null  # dependency structure

# Hot file analysis (most changed files recently)
git log --oneline --name-only -100 | grep -E '\.(go|ts|py|rs|java)$' | sort | uniq -c | sort -rn | head -20

This provides:

  • Package/module layout for better file-overlap detection
  • Hot files that are likely merge-conflict zones
  • Import graph hints for dependency inference

Phase 4: Dependency Inference

Dependencies are inferred using a layered heuristic system. Conservative by default — when unsure, serialize.

4.1 Explicit Dependencies (Highest Confidence)

Scan each issue body for:

depends on #N, depends on #{N}
after #N, after #{N}
requires #N, requires #{N}
blocked by #N, blocked by #{N}
must complete #N first
prerequisite: #N

These create hard edges in the dependency graph.

4.2 Semantic Type Ordering (High Confidence)

Issues are classified into types, and types have a natural ordering:

Layer 0 (Foundation):   schema, contract, interface, types, proto
Layer 1 (Security):     security, auth, rbac, policy, validation
Layer 2 (Core):         core logic, engine, service, handler
Layer 3 (Integration):  adapter, connector, plugin, loader, client
Layer 4 (Quality):      test, e2e, integration-test, benchmark
Layer 5 (Adoption):     docs, migration, rollout, config, ci/cd

Rule: An issue at Layer N is assumed to depend on any Layer <N issue that touches the same package/area, unless evidence suggests otherwise.

Classification heuristics (applied to title + labels):

  • Schema/Contract: title contains "schema", "contract", "interface", "types", "proto", "API", "model"
  • Security: title contains "security", "auth", "rbac", "policy", "validation", "permission"
  • Core: title contains "implement", "engine", "service", "handler", "core", "logic"
  • Integration: title contains "adapter", "connector", "plugin", "loader", "client", "integration"
  • Test: title contains "test", "e2e", "benchmark", "coverage"
  • Adoption: title contains "doc", "migration", "rollout", "config", "CI", "deploy", "README"

4.3 File Overlap Analysis (Medium Confidence)

For each issue, estimate which files/packages it will touch:

  1. Explicit paths mentioned in the issue body
  2. Package inference from keywords (e.g., "loader" → pkg/loader/, src/loader/)
  3. Codebase matching (if clone available) — grep for types/functions mentioned in the issue

When two issues have >50% file overlap, they should be serialized (same lane). When overlap is <20%, they can safely parallelize.

Between 20-50%: serialize (conservative default).

4.5 Hot File / Conflict-Prone File Warning

If codebase analysis is available, identify high-churn files (from git log) that appear in multiple issues. These are merge-conflict magnets.

# Top 20 most-changed files in recent history
git log --oneline --name-only -100 | grep -E '\.(go|ts|py|rs|java)$' | sort | uniq -c | sort -rn | head -20

For any file that appears in 3+ issues: Force serialization or add an explicit warning in the plan:

⚠️ CONFLICT RISK: pkg/engine/evaluate.go appears in issues #101, #103, #107
   → Serialize these or expect merge conflicts after each merge

Common conflict-prone patterns:

  • Go import blocks (parallel lanes both adding imports)
  • Registration/init files (blank imports, Register() calls)
  • go.sum / package-lock.json (always auto-resolvable, but flag them)
  • Shared constants/enum files

4.4 Keyword Cross-References (Low Confidence)

If issue #M's body mentions a type, function, or concept that is the primary deliverable of issue #N, infer #M depends on #N. Examples:

  • #N title: "Define PolicyDocument schema"
  • #M body: "Load PolicyDocument from YAML" → #M likely depends on #N

Phase 5: Lane Assignment Algorithm

5.1 Build the DAG

From Phase 4, construct a directed acyclic graph (DAG). If cycles are detected, break them by removing the lowest-confidence edge.

5.2 Topological Sort with Grouping

  1. Compute topological order of the DAG
  2. Assign each issue a depth (longest path from any root)
  3. Issues at the same depth with no mutual dependencies are candidates for parallelization

5.3 Lane Construction

Algorithm: Greedy Lane Assignment

1. Sort issues by depth (ascending), then by type layer (ascending)
2. Initialize empty lanes = []
3. For each issue I in sorted order:
   a. Find all lanes where I has no dependency conflict
      (I's dependencies are all in earlier positions of that lane or other lanes)
   b. Among valid lanes, pick the one with LEAST file overlap with I
   c. If no valid lane exists, or all have >30% file overlap, create new lane
   d. Append I to the chosen lane
4. Name each lane by its dominant theme (most common type classification)

5.4 Phase Assignment

Group lanes into execution phases:

| Phase | Contents | Entry Criteria | |-------|----------|----------------| | P0 | Foundation schemas, contracts, security | None — start immediately | | P1 | Core implementation that consumes P0 outputs | P0 complete | | P2 | Integration, adapters, connectors | Relevant P1 items complete | | P3 | Testing, e2e, benchmarks | P2 complete (or relevant P1) | | P4 | Docs, migration, rollout, CI/CD | P3 complete (or can start with P2) |

Issues within a phase can run in parallel across lanes.

Phase 6: WIP Limit Calculation

Recommended WIP = min(
  floor(sqrt(total_issues)),
  number_of_lanes,
  3  # hard cap for solo dev, 5 for team
)

For reference: 13 issues → WIP 2-3, 25 issues → WIP 3-4, 50 issues → WIP 4-5.

Factors that reduce WIP:

  • High file overlap across issues (merge conflict risk)
  • Many security-critical issues (need careful review)
  • Unfamiliar codebase

Factors that increase WIP:

  • Well-separated packages (microservice-like)
  • Strong test coverage (safe to parallelize)
  • Multiple developers available

Phase 7: Output Generation

Generate the execution plan markdown using the template in references/plan-template.md.

For each issue's Dev prompt, synthesize:

  1. Which files to create/modify (from file analysis)
  2. Key acceptance criteria (from issue body)
  3. Dependencies to be aware of (what contracts/interfaces to consume)
  4. Testing expectations
  5. Any gotchas from codebase analysis

Edge Cases

Epic with no task list

Fall back to milestone-based issue collection, or search for issues with a specific label.

Circular dependencies detected

Log a warning. Break the cycle at the weakest edge (lowest confidence heuristic). Add a note in the plan.

Issues with no body

Classify by title only. Add a warning in the dev prompt: "Issue body is empty — clarify requirements before starting."

More than 50 issues

Recommend splitting into sub-epics. Generate plan for the first ~25 highest-priority issues and note the remainder.

Cross-repo dependencies

Note them in the dependency graph with full org/repo#N syntax. These become external blockers, not lane-internal dependencies.

Example

Input:

repo: owner/repo
epic: #42
clone: true

Output structure (13 issues):

6 lanes (A-F), 5 phases, WIP limit: 2

Lane A (Contracts):     #1 → #5 → #9
Lane B (Security):      #2 → #6
Lane C (Core):          #3 → #7 → #11
Lane D (Loaders):       #4 → #8 → #12
Lane E (Testing):       #10 → #13
Lane F (Adoption):      #14

Phase 0: #1, #2          (contracts + security — no deps)
Phase 1: #3, #4, #5      (core + loaders consume contracts)
Phase 2: #6, #7, #8      (security integration + core features)
Phase 3: #9, #10, #11    (advanced contracts + testing)
Phase 4: #12, #13, #14   (final adapters + adoption)

Dev Prompt Authoring Guidelines

When generating dev prompts for each issue, follow these rules to avoid subagent failures:

  1. Keep prompts plain English — no shell metacharacters, no backticks, no heredocs, no nested quotes
  2. Reference code examples via files — if you need to show patterns, write them to a temp file and reference the path
  3. Be specific about file pathsCreate pkg/adapters/terraform/adapter.go not Create the adapter file
  4. Include the test commandRun: go test ./pkg/adapters/terraform/... so the agent knows how to verify
  5. Avoid $(), backtick substitution, or complex quoting in prompt text — these cause shell parse errors when the prompt is passed through an agent runner / CLI wrapper

Anti-pattern (breaks):

Implement the adapter using `func NewAdapter() *Adapter { return &Adapter{} }`

Correct (works):

Create a NewAdapter constructor that returns a pointer to Adapter. Follow the pattern in pkg/adapters/opa/adapter.go.

References

  • references/plan-template.md — Full output template with field descriptions