Stormwater Pollution Prevention Plan (SWPPP)

Produces a construction SWPPP covering site characterization, BMP selection, inspection schedules, recordkeeping, and operator certification under the Clean Water Act NPDES program.

Prerequisites

  1. Project details — name, location (coordinates or legal description), total disturbance acreage, timeline
  2. Operator identification — entity with day-to-day operational control
  3. Site characterization — soil types, topography, drainage patterns, existing vegetation
  4. Receiving waters — all water bodies receiving discharge, distance/direction, 303(d) or TMDL status
  5. Environmental features — wetlands, endangered species habitat, historic properties within or adjacent to site
  6. Existing permits — NPDES permit number, state CGP, MS4 requirements
  7. Site plans / grading plans — if available

Output Structure

1. Cover Page & Certifications

| Element | Requirement | |---|---| | Project name & NPDES permit # | Required | | Operator name, address, contact | Required | | Preparer name & qualifications | Required | | PE seal | If required by state | | Signature block | Operator or authorized representative — name, title, date | | Certification language | Full 40 CFR 122.22 certification language |

2. Site Description

  • Project narrative (scope, phases, timeline)
  • Total site area vs. disturbance area
  • Soil types (reference NRCS Web Soil Survey)
  • Pre- and post-construction drainage patterns
  • Receiving waters table:

| Receiving Water | Classification | 303(d) Listed? | TMDL? | Distance from Site | |---|---|---|---|---| | {name} | {class} | Y/N | Y/N | {ft/mi, direction} |

  • Endangered species / historic preservation eligibility determination

3. Best Management Practices (BMPs)

Organize into three categories. For each BMP, specify location, install timing, design spec, and maintenance requirement.

Erosion & Sediment Controls — silt fence, sediment basins (3,600 cf/acre or state requirement), inlet protection, stabilized construction entrances (min 50 ft × 20 ft, 6" stone), temporary seeding for areas inactive >14 days.

Good Housekeeping & Pollution Prevention

| Practice | Standard | |---|---| | Material storage | Secondary containment for liquids; covered erodible materials | | Concrete washout | Lined, bermed, ≥10 ft from drainage; no direct discharge | | Spill prevention | Kits within 50 ft of fuel/chemical storage; report per state thresholds | | Waste management | Dumpsters covered; hazmat manifested per RCRA | | Sanitary waste | Licensed portable facilities; serviced weekly minimum | | Vehicle maintenance | Drip pans required; fluid changes only over containment |

Stabilization Practices

| Condition | Deadline | Method | |---|---|---| | Inactive areas | 14 days from last disturbance (7 days if impaired water) | Temporary seed, mulch, or erosion blanket | | Final grade reached | Per CGP (typically 14 days) | Permanent seed + mulch or sod | | Steep slopes (>3:1) | Immediately after grading | Erosion control blanket + seed |

4. Inspection & Monitoring

Schedule

| Trigger | Frequency | |---|---| | Routine | Every 7 calendar days during active construction | | Storm event (≥0.5 in.) | Within 24 hours after discharge ends | | Reduced (if CGP allows) | Monthly when temporarily stabilized |

Inspector: Qualified person with SWPPP/BMP/CGP knowledge. States may require CPESC or equivalent.

Each inspection must document:

  • [ ] All BMPs operational and maintained
  • [ ] No off-site sediment discharge
  • [ ] Slopes and disturbed areas assessed
  • [ ] Sediment levels at basins/traps
  • [ ] Construction entrances functioning
  • [ ] Material storage properly contained
  • [ ] New discharge points identified
  • [ ] Prior corrective actions completed

Corrective actions: Initiate within 24 hours; complete before next storm or within 7 days, whichever is sooner.

5. Recordkeeping

| Record | Retention | |---|---| | Current SWPPP | Permit duration + 3 years; on-site or readily accessible | | Inspection reports, rainfall data, BMP maintenance logs | 3 years after Notice of Termination (NOT) | | SWPPP amendments (all versions) | 3 years after NOT | | Training records, agency correspondence | 3 years after NOT |

6. Amendments

SWPPP is a living document. Amend when:

  • BMPs prove ineffective
  • Site conditions change (new phases, redesign)
  • Inspections reveal new pollutant sources
  • Agency directs changes or operator changes

Log each amendment with date, description, and responsible party.

7. Personnel & Training

  • Identify SWPPP administrator by name and contact
  • All BMP personnel: initial training + annual refresher
  • Topics: SWPPP requirements, BMP installation/maintenance, spill response, reporting obligations

8. Appendices

  • A: Site maps (existing conditions, grading, BMP locations, drainage areas)
  • B: BMP detail drawings
  • C: NPDES permit / state CGP authorization
  • D: Notice of Termination (when filed)
  • E: Inspection report forms (blank + completed)
  • F: Subcontractor certifications
  • G: Endangered species / historic preservation documentation

Guidelines

  • State tailoring — CGP varies by state; confirm BMP design standards, inspection frequencies, stabilization deadlines, and reporting thresholds [VERIFY]
  • 303(d) / TMDL waters — trigger enhanced BMPs and potentially numeric effluent limits; flag prominently in site description
  • MS4 permits — check for local requirements beyond the CGP
  • Multi-operator sites — each operator needs own SWPPP or clearly defined responsibilities in shared plan
  • Do not certify — include signature blocks but operator (not drafter) must sign
  • Linear projects (roads, utilities) — use phased approach with separate BMP plans per active segment
  • Federal citations: 40 CFR § 122.26, 40 CFR § 450.21, CWA § 402 [VERIFY CGP version year against current EPA issuance]
  • Mark all state-specific citations with [VERIFY] unless user provides applicable state CGP