v-and-v-manager

通过将技术评估与系统需求关联来管理验证和确认(V&V)过程。使用此技能构建验证控制矩阵(VCM),跟踪合规状态,并确保所有需求都有证据支持。触发词包括“验证矩阵”、“VCM”、“合规检查”、“需求关闭”或“验证状态”。

person作者: jakexiaohubgithub

V&V Manager Skill (Verification & Validation)

Read CONVENTIONS.md at the repo root before proceeding.

This skill closes the engineering loop. It compares "As-Required" (from requirements-manager) against "As-Analyzed" or "As-Tested" (from domain skills and ait-manager).

Before You Begin

Ask the user (if not already known):

  1. What V&V standard applies?
    • NASA: NPR 7123.1 (SE Processes), NASA-STD-8739 series
    • ESA: ECSS-E-ST-10-02 (Verification)
    • INCOSE: Systems Engineering Handbook Ch. 12
  2. What design phase? (Determines which verification methods are expected to have evidence)
    • Phase A/B: Analysis only — most items will be OPEN
    • Phase C: Analysis and some inspection
    • Phase D: Test evidence becomes available
  3. Where are the analysis outputs stored? Default: /analysis/[skill-name]/

Applicable Phases

  • Primary: Phase B (verification planning), Phase C/D (verification execution and closure)
  • Supporting: Phase A (define verification approach per requirement)

Core Workflow

1. Requirement Lookup

  • Scan /requirements/ for ### [REQ-ID] headers.
  • For each requirement, identify the specified Verification Method: Test, Analysis, Inspection, or Demonstration (TAID).

2. Evidence Retrieval

  • Search /analysis/ for corresponding output files.
  • Match logic:
    • REQ-PWR-* → look in /analysis/power-assessment/
    • REQ-THR-* → look in /analysis/thermal-assessment/
    • REQ-STR-* → look in /analysis/structural-assessment/
    • etc.
  • If evidence exists: compare the result against the requirement threshold.
  • If evidence is missing: flag as OPEN and recommend which skill to run.

3. Phase-Appropriate Expectations

| Verification Method | Phase A | Phase B | Phase C | Phase D | |:---|:---|:---|:---|:---| | Analysis | OPEN (expected) | Should have evidence | Must have evidence | Must have evidence | | Test | OPEN | OPEN | OPEN (test planned) | Must have evidence | | Inspection | OPEN | OPEN | May have evidence | Must have evidence | | Demonstration | OPEN | OPEN | OPEN | Should have evidence |

4. VCM Generation

Create a master table:

| ID | Requirement | Method | Evidence File | Status | Notes | |:---|:---|:---|:---|:---|:---| | REQ-PWR-001 | Battery ≥ 1500 Wh EOL | Analysis | power_analysis.md | 🟢 PASS | 1620 Wh predicted | | REQ-THR-003 | Battery 0-30°C operating | Analysis | thermal_model.md | 🟡 OPEN | Pending thermal run | | REQ-STR-010 | First freq > 25 Hz | Test | — | 🔴 OPEN | No test yet |

Compliance Rules

  • PASS 🟢: Evidence exists and values meet requirement (including margins).
  • FAIL 🔴: Evidence exists but values exceed limits.
  • OPEN 🟡: No evidence yet or evidence is from a previous design iteration.
  • WAIVER: Requirement formally relaxed with documented justification.

Output Format

  1. Verification Control Matrix (vcm.md): Master tracking table.
  2. Analysis Requests: List of "To-Do" assessments to close OPEN requirements.
  3. Compliance Summary: Overall percentage of PASS/FAIL/OPEN, with traffic light status.

Interface

  • Reads from: /requirements/, /analysis/*/ (all domain skill outputs), /analysis/ait-manager/ (test evidence)
  • Writes to: /analysis/v-and-v-manager/
  • Consumed by: Review boards (SRR, PDR, CDR), project management